Why we ask so many questions early

Most problems with a veranda or glass room aren't about the structure. They come from something nobody mentioned until it was already built. A few minutes now saves changes, delays and extra cost later. For example:

  • A hot tub planned for later needs its own base and headroom
  • TV and heater cables need hiding inside the frame before it goes up
  • Glass sliding doors need a level strip, and most patios slope
  • A wide glass roof may need a middle post or a reinforced gutter
  • Doors that open outwards must clear the posts and side walls
  • A gas flue or meter on the wall has to be moved first

Tell us early and we can plan for it. Tell us after it's built and the options get much smaller.

How it works

1

Read this guide

Skim the sections below and note anything that applies to you. You don't need every answer, just the ones you know.

2

Send us photos

Use the photo list further down the page and send them by WhatsApp or email. They help us spot anything unusual before we visit.

3

Free site survey

We measure up, check the wall, ground, levels and drainage, and talk through the options that suit how you'll use it.

4

Your written quote

You get a clear written quote showing what's included and anything you'll need to arrange before installation day.

The survey checklist

Tap a section to open it. Each one lists the questions we'll ask and why they matter.

Part 1

Your plans

Tell us how you'll use it and what you'd like. These answers shape which model we recommend.

1 How you will use itWhat it's for, when you'll use it and what needs to fit under it.
  • What will you mostly use it for? Eating outside, relaxing, children playing, covering a hot tub, drying washing, working from home, entertaining, a gym, parking or storage?
  • When will you use it? Summer evenings only, or most of the year?
  • How many people, and what furniture will go under it?
  • Do you want an open shelter, or something you can close up like a room?
  • Do you need shade from the sun, cover from the rain, or both?
  • Does privacy from neighbours matter?
  • Will you use it after dark?
  • Will you want to heat it?
  • Do you have pets or plants that need light, shade or airflow?
2 Turning it into a roomGlass sides, flooring, TVs, air con, gyms, hot tubs and heating.

Many customers turn their veranda into a garden room. Planning this now helps us recommend the right model and add-ons.

  • Will it have glass sides or doors all round, or stay partly open? Fully enclosed means glass sliding walls or doors on every open side, and possibly building regulations.
  • New flooring, such as tiles, porcelain, composite decking or rubber gym flooring? Lay it before installation, keep it level where sliding door tracks will sit, keep 200mm of solid concrete under each post, and give it a slight fall away from the house.
  • Artificial grass? Posts must go through to solid concrete, not sit on the grass. Lay it after installation, cut around the posts, and keep a hard, level strip under any sliding door track.
  • A TV, speakers or projector? Decide the position before ordering so power and data cables can be hidden in the frame. South or west-facing rooms may need tinted glass or blinds for glare. Use an outdoor-rated TV unless the room is fully enclosed.
  • Air conditioning? It only works well in a fully enclosed glass room, and veranda roofs are not insulated, so it will work hard in summer. Plan where the outdoor unit, pipework and condensate drain go. The roof cannot carry the unit. Solar control glass and external blinds reduce the load.
  • A home gym? Plan headroom for lifting or a rig, a solid level floor for heavy kit, ventilation through opening doors or louvres, rubber flooring and power points.
  • A hot tub inside or under it? It needs its own base rated for its full weight with water and people, separate from the post footings. Check headroom for the cover lifter and getting in and out. Steam and chemicals need plenty of ventilation, so never fully seal it. Plan the delivery route, ideally before the structure goes up. It needs its own electrical supply. Wash the frame regularly, as chlorine is hard on finishes.
  • Heating? Electric infrared heaters designed for covered spaces only, never gas or open flame. Plan positions and power before ordering.
  • An outdoor kitchen, sink or plants inside? Plan plumbing and drainage first, and keep cooking appliances away from the roof and glass.
  • A study, playroom or office? Run power and internet before installation, and plan blinds for screen glare and heating or cooling for comfort.
  • Everything in this step (flooring, TVs, air conditioning, hot tub bases, electrics, plumbing) is arranged by you with the right trades, before or after installation day.
3 Bigger plans, budget and timingBigger projects, future add-ons, budget and timing.
  • Is it part of a bigger project, such as a new patio, an extension or landscaping? When is that happening?
  • Might you add glass doors, side walls, lights or heaters later? If so, we plan for them now.
  • Are you planning to sell the house in the next few years?
  • What view and light from inside the house do you want to keep, for example a kitchen or living room behind it?
  • What are your must-haves and nice-to-haves?
  • What budget range are you working to? It helps us suggest the right model first time.
  • When would you like it finished? Is there a date you are working towards? Allow for lead times, which are estimates and vary by brand.
4 What you would likeType, roof, sides, extras and colour, plus sliding doors and glass.
  • What type: veranda, glass room, louvred pergola, carport or awning?
  • What roof: glass or polycarbonate, clear or tinted, or louvres? Glass is quieter in rain and stays clearer. Polycarbonate is lighter and cheaper but noticeably louder in heavy rain.
  • What sides: open, glass sliding doors, fixed glass, side walls, screens or blinds?
  • Which extras: LED strip lights, spotlights, heaters, motorised roof or screens?
  • Which frame colour: anthracite, black, white or another? Dark colours get hotter in sun.

Glass sliding doors and side elements

  • Glass sliding doors sit on a rail at the bottom and are held in a top profile. Each door can run on its own track, or several doors can share a track on wider openings.
  • Rail systems come from 1 track up to 7 tracks wide. More tracks means more panels can slide past each other and stack neatly.
  • How do you want them to open: meeting in the middle, or sliding to one side? Where should the panels stack so they do not block a view, a door or furniture?
  • Spare tracks can carry other accessories, not just glass. For example, louvre panels on the outer tracks with glass doors on the inner tracks give shade and privacy while the glass still slides.
  • A single rail currently spans up to 7m. Wider openings are possible by adding a post part way along, or by joining two rail systems together.
  • The rails are designed to shed water outwards and the doors sit on a slight slope. This does not affect how they slide, but helps water drain from between the doors.
  • Brushes between the doors and in the top profile, plus a small overlap between panels, help keep out dust, wind and insects. The top profile allows some tolerance so the doors can move slightly with the structure. They reduce the weather but do not fully seal it out.
  • If fitting them yourself: each panel is lifted into the top profile, then lowered onto the bottom rail. It needs at least 2 people, the right tools such as glass suction cups, and safety equipment such as gloves, safety boots and eye protection. The bottom rail must be level and fully supported first.

Ordering glass for side walls and infills

  • Some of our products come pre-made. Glazed side walls, for example, arrive made to fit your structure, with no cutting or glass measuring. The only measurement you need is the original size of the structure.
  • Other infills, such as gable triangles and custom panels, may need glass ordered separately. Ask us which applies.
  • If ordering your own glass, tolerances are tight. Manufacturers often specify around 5mm, so a small mistake means glass that does not fit.
  • Method 1, manufacturer's method: order glass to the manufacturer's sizes and tolerances, then assemble it with the profiles around the outside. Highest risk, as sizes must be exactly right first time.
  • Method 2, profiles first with glazing beads: fit the outer profiles first, then put the glass in from outside and hold it with glazing beads. Lower risk, as beads give more tolerance.
  • Method 3, profiles first then measure: fit the outer profiles, measure the actual openings, then order the glass. Lowest risk, as you know the finished sizes for certain.
  • Always use safety glass (toughened or laminated) and follow the manufacturer's instructions for gaps, setting blocks and sealing.
Part 2

The structure

Sizes, heights and how it fixes to your house.

5 Size, position and clearancesWidth, projection, door swings, wall height, roof pitch, spans and movement.
  • How wide along the house, and how far out, in millimetres?
  • Fixed to the house, or freestanding on its own posts?
  • Where would the posts go? Is anything in the way, such as paths, steps, drains or manholes?
  • Would you prefer no middle post?

Doors and windows

  • Do any doors or windows open outwards into the area? How far do they swing out?
  • Posts, side beams, side walls and glass doors must sit clear of these so everything can still open fully.
  • Where do you want the way in and out of the structure, and does it line up with your house doors?
  • Do any doors have steps or a raised threshold outside them?
  • Are there first-floor windows above? The wall profile must sit between the top of the ground-floor doors and windows and the bottom of the first-floor window sills, gutter or soffit.

Height at the wall

  • How much clear wall is there between the top of your highest door or window and the bottom of the gutter or soffit? The wall profile needs about 12 to 20cm.
  • Does the wall height change along its length, for example where an extension, bay or lower roof meets the main house?
  • Is there a sloping roof, conservatory or porch on that wall that the structure has to fit under or around?

Roof pitch: the limits and the flexibility

  • Pitched verandas are generally designed for a 9 degree roof pitch, to the manufacturer's spec. That slope makes rain run off cleanly into the front gutter.
  • With too little slope, water sits and beads on the roof, and can creep back round under the roof edge by surface tension and drip inside the structure.
  • At 9 degrees the roof drops about 15cm for every metre it comes out: about 45cm over 3m, 60cm over 4m and 75cm over 5m.
  • Front height = height where it fixes to the house, minus the drop. Mounted at 3m with a 5m projection, the front is about 2.25m. Mounted at 2.5m with a 5m projection, the front is about 1.75m, which is too low to walk under comfortably.
  • It works best with projections up to about 5m and a mounting height up to about 3m, where planning allows.
  • If the front would be too low, options include a shorter projection, a flat-roof or low-height model, mounting above the fascia, freestanding posts at the back, or a slight reduction in pitch below 9 degrees. A reduced pitch can work, but water sheds more slowly and is more likely to bead or run back under the edge. We explain the trade-off before anything is ordered.
  • Each model has its own minimum and maximum heights at the wall and at the front. Some have a fixed pitch, others are designed as flat roofs for low walls such as bungalows.

Spans, posts and the gutter

  • The front gutter is also the beam that carries the roof between the posts. Depending on the model, spans between two posts range from about 4m up to 6 or 7m, and on some models 8m.
  • If the gutter is not strong enough for the span and roof weight, it can deflect (sag slightly) near the middle. That makes a low spot where rainwater sits instead of running to the outlet in the post.
  • Some aluminium models have a specially shaped gutter that can span 6 to 7m on two posts with no steel reinforcement. Others need a steel-reinforced gutter to reach longer spans, and only some models offer one.
  • A glass roof is much heavier than polycarbonate, so across a 4 to 7m span it often needs a steel-reinforced gutter.
  • Options for a wide opening: add a middle post (usually easiest and most cost-effective), a steel-reinforced gutter (keeps the view clear), or a model engineered for long spans.
  • How wide overall? Would you accept a middle post, or is a clear view important? Where would a middle post sit, and is it in front of a door, path or the best view?

Thermal movement

  • Aluminium and glass expand slightly when warm and shrink back when cool, in every direction. Aluminium moves more than glass. As a rough guide, a 6m aluminium beam can change length by around 5mm between a cold winter night and a hot summer afternoon.
  • Do not build the structure hard against a fence, boundary wall, neighbouring building, shed or another structure. Leave a small gap.
  • Seal against the house with flexible silicone, not rigid mortar or filler. Avoid fixing anything rigid that the structure would push against, such as tiles, boxing-in or decking boards tight to the posts.
  • It is more noticeable on south and west-facing structures, dark frame colours, and long runs. Occasional light ticking or creaking as the temperature changes is normal.
6 The house wall and how it is fixedWhat your wall is made of, its condition and how it will be fixed.
  • What is the wall made of: solid brick, concrete block (solid or hollow), render, pebble-dash, stone, timber or cladding, or a mix?
  • Is it the main house, or a garage, porch or older extension with a single-skin wall?
  • Is it in good condition, or is there loose render, cracked bricks, crumbling mortar or damp?
  • Does the house have external wall insulation under the render? It needs special fixings, so tell us.
  • Why it matters: not every wall can carry the same load, and each material needs a different fixing. A glass roof is heavier than polycarbonate. That is why fixings into your wall are not supplied with the kit: they are chosen to suit your wall. Some walls cannot take the load, in which case the answer is a freestanding structure or a different fixing position.
  • How it is fixed: most wall-mounted verandas have a wall profile along the house, usually 12 to 20cm tall. Bolts go through it into the wall, usually set in resin on masonry, which grips very strongly once it cures. Render and pebble-dash are drilled through into the solid masonry behind. Hollow blocks need hollow-wall fixings. Timber, cladding, soffits and fascias are not fixed into directly; the fixing goes into the structure behind, above the fascia with purpose-made brackets, or the structure becomes freestanding.
  • Keeping water out behind the profile: a strip of water-resistant foam behind the profile plus a bead of silicone along the top stops water running down the back. On pebble-dash, uneven brick or stone, this may need more work, and some walls also need lead flashing.
  • What is fixed to the wall where the profile would go: lights, cameras, alarm box, satellite dish, vents, airbricks, flues, taps, downpipes or meters? These need moving by the right trade before installation day.
Part 3

Your site

The ground, water, services and power. Most surprises on installation day start here.

7 The ground and baseWhat's there now, how level it is and how the posts will be fixed.
  • What is there now: patio, concrete, lawn, gravel, soil, decking, or a raised balcony?
  • Is there at least 200mm of solid concrete under where the posts would go? Lift one slab to check.
  • Is the patio sound, or cracked, sinking or rocking?
  • Keep any new patio or flooring at least 150mm below the damp proof course of the house, and never cover airbricks.

Is it level?

  • Most patios slope away from the house, and decking and balconies often slope or sag too.
  • How much does it fall from the house outwards, and from side to side? Measure with a spirit level and a long straight edge and send us the drop in millimetres.
  • Is there a step down from the inside floor to the patio, and how big is it?
  • An open veranda copes with a slope easily, because the posts are cut to suit. Glass sliding doors, fixed glass walls and rigid side panels need a level surface.
  • On a sloping base, the bottom track or frame must be levelled first, with a long tapered packing strip such as a uPVC wedge strip along the whole length, or with groundwork to create a level strip. Never sit glass on a few small shims, as the track can flex.

How the posts are fixed

  • Bolted onto existing concrete: posts are pre-cut to length and bolted to a solid base.
  • Set into the ground: posts are pre-cut to go below ground, so they come up flush through the patio, which can then be tiled or paved around them.
  • Cut on site: some posts come uncut and are cut to suit on the day, above or below ground. Useful where levels vary.
  • On grass, soft or boggy ground: ground screws are a good option, screwed deep into the ground for a solid footing without a large concrete pour. Or a precast concrete foundation can be dug in at each post, set on poured concrete, then backfilled and finished to level.
  • On decking: composite decking is recommended over timber. It does not rot, is stronger, and moves less. Composite decking built correctly for the weight of your chosen veranda can be just as structurally sound as a properly laid concrete base. The frame and joists must be designed for the load, especially under each post. For a raised balcony, a structural engineer may need to check it can take the load.
8 Rainwater and drainageWhere the rain goes, from the wall to the roof to the ground.
  • On the wall, rain runs down the house. The wall profile at the top of the veranda directs that water onto the roof.
  • On the roof, water runs into the gutter and down through one or more posts.
  • On the ground, dips, high spots or uneven areas mean water can pool on the patio, under the structure or against the house. After rain, does water sit anywhere? Correct the base before installation day, or plan where surface water will go, such as a channel drain or gravel strip.
  • How much water? 1mm of rain on 1 square metre is 1 litre. A 6m x 4m roof in a 10mm downpour sends about 240 litres down the posts.
  • Which post should the water come out of, and which way should it run? Choose the side nearest a drain or the garden.
  • Options: an underground pipe to a drain or soakaway (tidiest, put in before installation day), an above-ground downpipe to a drain or gully, or a water butt to use on the garden with an overflow for when it is full. Never let it simply spill onto the patio next to the house.
  • If the structure would sit over a public sewer or shared drain, you may need approval from your water company first.
  • If you choose underground drainage: the veranda's drain has a leaf catcher, so larger debris is mostly stopped, but fine sediment can still settle in pipes over the years. Ask your groundworker to fit an access point such as a rodding eye or inspection chamber, and do not bury it under paving, decking, artificial grass, a hot tub or the structure. Check the leaf catcher when you clean the gutter. If water backs up, the pipe may need rodding or jetting.
9 Water, sealing and what to expectHow sheltered it will be and where water can still get in.
  • A veranda, pergola or glass room is a sheltered space, not a sealed extension. In heavy or wind-driven rain, some water can get in at the edges, under door rails and around side panels. That is normal for these systems, not a fault.
  • Where it meets the house: the roof-to-wall joint is sealed, usually with silicone and sometimes lead flashing. Where a glass side panel or sliding door meets the wall, the gap is sealed with silicone. On pebble-dash or uneven brick the seal has to fill a bumpy surface and may need more work.
  • Silicone is a maintenance item. Check it each year and top it up from inside or outside if it cracks or pulls away.
  • Along the floor: glass panels and sliding door rails are screwed down to your existing floor. The bottom rail is a raised hollow section, so there is no seal underneath it, and some water can get under it in bad weather. Some systems have drainage outlets inside and outside the rail, and some tilt slightly outwards so water drains away.
  • Around the posts and frame: glazing and side panel profiles inside the posts and frame are screwed in place with no weather-tight seal, so some water or draughts can come through in strong wind and rain.
  • Condensation can form on the inside of glass in cool or damp weather, especially in a fully enclosed room. Good ventilation helps.
  • Want it more weather-tight? Tell us at the survey how sealed you need it to be, for example for a gym, office, tiled floor or electronics, and we will talk through options before you order.
10 Hidden servicesPipes, cables, drains, gas and flues near the posts or wall.
  • Are there pipes, cables, drains, soakaways or manholes under the patio or near the post positions?
  • Are there cables or pipes in the wall where it would be fixed?
  • Is there a gas pipe, meter or boiler flue on that wall? A Gas Safe registered engineer must check and move it if needed. We do not carry out gas work.
11 Electrics, lighting and powerLights, heaters, motors and sockets, and where the cables run.

We do not carry out electrical work or make the final connection. A qualified, Part P registered electrician does this after installation.

  • What needs power: LED strip lights, spotlights, heaters, motorised roof or screens, a TV or speakers, sockets, a hot tub?
  • Where should lights run, and do you want even light over a table or soft light round the edge?
  • Where should heaters sit so they warm where people sit, at a safe distance from glass and roof?
  • Where do you want switches or controls: a remote, a post, inside the house, or your phone?
  • Plug-in or hardwired? Some lights and heaters come with a plug and only need an outdoor socket nearby. Others need hardwiring into your home's electrics. Do not cut off or change supplied plugs, leads or drivers, as that can void the warranty.
  • Would you rather the cables were hidden, or would you mind some being visible? Hidden cables usually run inside the beams and down a post, but this must be planned before the structure goes up.
  • How will the cable get from the post to the house: trunking along the wall, a duct under the patio, or through the wall?
  • Where will any driver, transformer or control box sit?
  • Where is your consumer unit, is there room for a new circuit, and will you need an outdoor isolator or a dedicated circuit for heaters, a hot tub or air conditioning?
  • Decide all of this before you order. Once the frame is up, hiding cables is much harder.
Part 4

Comfort through the seasons

Keeping it cool in summer and usable in winter. Decide this early, because shading, glass and floors are hard to change later.

12 Keeping it cool: sun, glare and heatSolar control glass, external and internal shading, and ventilation.

A glass roof lets in a lot of sun. On a south or west-facing house in summer, an unshaded glass room can get much hotter than it is outside, even on a mild day. Some shading and glass choices have to be made when the structure is ordered, so plan them now.

How the heat builds up

  • Sunlight passes through the glass and warms the floor, furniture and frame. They give that heat off again, and it can't escape back out through the glass as easily as it came in. That's why an enclosed glass room heats up so quickly.
  • An open veranda lets air move through freely. Enclose every side with glass and far more heat is trapped.
  • Dark frames, flooring and furniture soak up more heat than light ones.

Tinted glass is not solar control glass

  • Tinted glass, such as grey or bronze, mainly cuts brightness and glare. It doesn't necessarily stop much of the heat, and some tinted glass absorbs heat and gets warm itself.
  • Solar control glass has a coating or specification designed to reflect part of the sun's heat away. It's judged by its solar performance, often shown as a g-value or solar factor (the lower the figure, the less heat gets through), not by its colour.
  • If heat matters to you, ask for solar control glass by name and check it's written on your quote. Don't assume tinted or anti-glare glass will keep the room cool.
  • Some polycarbonate roofs and side walls come in solar control versions too. Opal panels soften the light and cut glare, but aren't the same thing.

Shade on the outside works best

  • Shading outside the glass stops the heat before it gets in. Shading inside cuts glare and some heat, but by then much of the heat is already inside.
  • Above-roof awnings sit on top of the glass roof and are the most effective way to keep a glass room cool.
  • Under-roof blinds are protected from wind and rain and look neat. They're good for glare and take the edge off the heat.
  • Vertical blinds and zip screens on the front and sides block low morning and evening sun, which roof shading can't reach.
  • Louvred roofs and louvre side panels let you angle out direct sun and still keep the air moving.
  • Motorised shading can be fitted with sun and wind sensors so it opens and closes by itself. Plan the power and controls before installation (see Electrics).
  • Shading also changes how much daylight reaches the room behind, so think about the kitchen or living room too.

Let the heat out

  • Ventilation matters as much as shade. Hot air rises and collects under the roof, so openings both high and low get air flowing through.
  • Sliding doors that open fully on more than one side make the biggest difference on hot days.
  • Some models offer opening roof sections or louvres, and ceiling fans can be fitted to some frames. Ask us what your chosen model allows before planning on them.
  • Thinking about air conditioning? Shade first, then cool. See Turning it into a room.

Questions we'll ask

  • Which way does it face, and what time of day will you use it most?
  • Will it be open, partly enclosed or fully enclosed?
  • Does the room behind it already get too hot, or too dark?
  • Is glare a problem for a TV, screens or the kitchen?
  • Would you rather shade it from outside, inside or both, and do you want it motorised?
13 Keeping it warm: holding heat inWind, insulated doors, floors, underfloor heating and heaters.

A veranda or glass room is a sheltered space, not an insulated extension, and the roofs are not insulated. Even so, a few decisions made at the planning stage make a big difference to how much of the year you can use it. Several of them link to other sections: the ground and base, water and sealing, and electrics.

Be realistic about what you're building

  • An open veranda: you're warming people, not air. Radiant heaters and something to block the wind work best.
  • A fully enclosed glass room: it holds some heat, but glass loses heat much faster than an insulated wall, and the joints aren't sealed (see Water, sealing and what to expect). Plan to heat it while you're using it, rather than keep it warm all the time.

Stop the wind first

  • Wind takes heat away faster than anything else. A side wall, fixed glass or sliding doors on the exposed side, often just one side, makes an open veranda feel much warmer.
  • Brushes and overlaps on sliding doors cut draughts but don't seal them. Insulated sliding doors, windows and front doors are available on some systems if you want a warmer, more enclosed room. The roof itself is not insulated.
  • Tell us which side the wind usually comes from at the survey.

The floor: plan it before the base goes in

  • A cold floor makes the whole space feel cold, and a lot of heat is lost down into a bare concrete slab or patio.
  • If a new base is going in, ask your groundworker about insulation and a damp proof membrane under the slab. It has to go in at the start and can't be added afterwards. The posts still need at least 200mm of solid concrete underneath, so keep insulation out of the post footings (see The ground and base).
  • Underfloor heating, either electric mats or a wet system, can go into a new screed or under tiles. It gives gentle, even warmth and helps keep the floor dry. It only works efficiently over an insulated base, and it has to be planned with the base, the post positions and the electrics. Keep pipes and cables well clear of the post footings and anything screwed into the floor, such as sliding door rails.
  • Keep the finished floor level where sliding door tracks will sit, and at least 150mm below the damp proof course of the house.
  • A raised composite deck with insulation between the joists is warmer underfoot than bare concrete.
  • Outdoor rugs and soft furnishings help more than you'd expect.

Heating it

  • Electric infrared heaters warm people and surfaces directly rather than the air, so they work well in open and partly open spaces and give heat straight away. Fix their positions and power before ordering (see Electrics). Only use heaters designed for covered spaces, at the distances from glass and roof the maker sets out, and never gas or open flame under the roof.
  • Underfloor heating suits a fully enclosed room you use often.
  • A heat pump air conditioner can heat an enclosed glass room as well as cool it, but it will work hard because the roof isn't insulated.

Make the most of free heat

  • The sun warms a glass room even in winter. Shading you can retract lets low winter sun in and keeps high summer sun out.
  • Clear glass lets in the most winter warmth. Solar control glass cuts summer heat but also some of that winter gain, so think about which season matters more to you.
  • Warm, moist air meeting cold glass causes condensation. The warmer you keep it without fresh air, the more condensation you'll get, so keep some ventilation (see Water, sealing and what to expect).

Questions we'll ask

  • Which months do you want to use it, and for what?
  • Is a new base or new flooring going in, and when?
  • Would you consider underfloor heating, heaters, or both?
  • Which side does the wind usually come from?
  • Would you like insulated doors or windows on any side?
Part 5

Before installation day

Access, upkeep, exposure and permissions.

14 Access for delivery and installationGetting long parts from the road to your garden.
  • How do we get from the road to the back garden: side gate, passage or through the house? How wide, and are there steps?
  • Can parts 4 to 7m long get through?
  • Is there parking or space to unload, and any restrictions?
  • Are there overhanging trees, hedges or overhead wires?
  • Is there a working socket for tools on installation day, and someone aged 18 or over at home at the start and finish?
  • Installation can be postponed in high winds or heavy rain for safety.
15 Access for cleaning and maintenanceReaching the roof, gutter and posts to keep them clean.
  • A glass roof needs cleaning about as often as your windows, but because it sits at a gentle slope, dirt settles instead of running off. Leaves, bird droppings, pollen, dust and salt end up on the roof and in the gutter.
  • Clean the roof, gutter and drainage at least twice a year, and every three months near the coast, trees, pollution or a pool. Check the gutter after autumn and after storms.
  • Can you get a ladder to the front gutter on firm, level ground, along the front and both ends? Is one side tight against a fence or boundary?
  • Can you reach the bottom of each post to clear the drainage outlet?
  • Never stand, kneel or walk on the roof. Use a soft brush or water-fed pole from a ladder or the ground, with clean water and mild detergent. No harsh chemicals, abrasive pads or close-range pressure washing.
  • In heavy snow, clear the roof gently from the ground with a soft brush where safe, and never climb on it.
  • Think about where a ladder will go when planning flower beds, ponds, hot tubs or furniture.
16 Location and exposureWhich way it faces, wind, snow and distance from the sea.
  • Which way does it face? South and west get hot, so solar control glass or blinds help. North-facing stays cooler and darker.
  • Will it make a room behind it darker? Clear glass keeps the most light.
  • Is it windy or exposed, such as open fields, a hilltop or a gap between buildings?
  • Do you get heavy snow? Snow and wind loads affect which model suits.
  • Are you within 5km of the sea or 1km of a swimming pool? The paint warranty is shorter there and the structure needs cleaning more often.
  • Could the roof make it easier for someone to climb to first-floor windows? Consider window locks if so.
17 Permissions and what is there nowPlanning, building regulations, boundaries and anything to remove.
  • Checking and getting any permission is your responsibility. Ask your local council before ordering. We can supply drawings to help.
  • Are you in a conservation area, a listed building, a flat or maisonette, or an area with an Article 4 Direction? These usually remove permitted development rights.
  • How close is it to the boundary, and how tall will it be? Height limits are tighter within 2m of a boundary.
  • Will it cover a large share of your garden, or sit forward of the front of the house? Both can affect permission.
  • Would it be fully enclosed, so building regulations might apply?
  • Do you need landlord or freeholder consent, or are there restrictions in your deeds?
  • Is a shared wall or boundary involved? A party wall agreement may be needed, and it is worth talking to neighbours early.
  • Tell your home insurer about the new structure.
  • Is there an old structure to remove first? We do not remove these. Any waste must go with a registered waste carrier, which you can check on the government's public register.
  • Are there old fixings, plants, furniture, a hot tub or a shed in the way?

Photos to send us

Clear photos help us check your space before the visit. Add a tape measure or spirit level where it helps show a size or a slope.

  1. The full width of the back of the house.
  2. Close-ups of the wall surface where the profile would go, and the gap between the top of the door and the gutter, with a tape measure.
  3. The patio surface and one lifted slab showing the base depth.
  4. A spirit level on the patio pointing away from the house and one across the width, with a tape showing the gap.
  5. Underneath any decking, if you can get to it.
  6. Any doors or windows that open outwards, open fully.
  7. The access route from the road.
  8. Any drains, manholes or downpipes nearby.
  9. Any water pooling after rain.

What happens at the site survey

There's no charge and no obligation to go ahead. Have your answers and photos to hand and we'll go through the rest together.

  • We measure up and check the wall, the base, the levels, the clearances and the drainage.
  • We bring samples of finishes and colours.
  • We talk through how you will use it and the options that suit.
  • We confirm what is included, and what you will need to arrange before installation day.
  • You get a clear written quote with no obligation.

Installation is carried out by us or on our behalf across Leicestershire and the surrounding counties, and further afield subject to availability. Ordering supply only? Read our Self Assembly Guide and Supply Only Agreement.

Ready to book your survey?

Call 03330 907890 (Monday to Friday, 10:00 to 16:30), email sales@romaverandas.com or message us on WhatsApp with your photos.